CIDB Fourth Schedule Act 520 Amendment 2026: What Changed and Who It Covers

The Lembaga Pembangunan Industri Pembinaan Malaysia (Amendment of Fourth Schedule) Order 2026, P.U. (A) 277/2026, came into operation on 1 August 2026. It replaces the whole Fourth Schedule of the Construction Industry Development Board Act 1994 (Act 520). The new schedule lists construction materials in 11 categories, each against its approved standards. Under section 33D of Act 520, dealing in a listed material without CIDB certification is an offence, with a fine of not less than RM10,000 and not more than RM500,000.

This page is general information about the CIDB Fourth Schedule amendment. It is not legal advice. Confirm the gazette and the facts of a given SKU or contract with CIDB, a licensed advisor, or counsel.

The gazetted order, P.U. (A) 277/2026, carries the full list of products and approved standards.

What the Fourth Schedule controls

Act 520 created CIDB. Under section 33C of Act 520, CIDB certifies the construction materials in the Fourth Schedule against the standards listed there. Section 33D bars dealing in a listed material that CIDB has not certified. The 2026 Order amends that list. Duty and SST remain a Customs matter under PDK 2025, covered in the building material import duty and SST 2025 guide. A listed product can need CIDB certification and still attract duty, SST, or both.

What changed on 1 August 2026

Paragraph 2 of P.U. (A) 277/2026 substitutes a new Fourth Schedule. Its 11 categories are iron and steel; concrete; aluminium; cement; ceramic, sanitary wares and clay; fibre and composite; glass; insulation material; radiant barrier; timber; and innovative product.

The full list can be compared with the 2021 order, P.U. (A) 358/2021.

Some materials listed in 2021 now carry more standards. Portland cement other than white Portland cement was listed against MS EN 197-1 in 2021, and the 2026 order lists MS EN 197-1, BS EN 197-5 and BS EN 15743. Certificates already on file are worth checking against the new list.

Who the Act covers

Section 33D of Act 520 applies to any person who deals or undertakes to deal in a Fourth Schedule material. Section 2 of the Act defines “deal” as to handle, use, manufacture, supply, market, transfer, sell or buy, whether wholesale or retail, import or export.

  • Manufacturers who make a listed product in Malaysia fall under “manufacture”. The manufacturers directory maps who produces a category. Typical diligence records the mill’s PPS number, standard, and expiry date.
  • Importers and exporters of listed products fall under “import” and “export”. Customs clearance is a separate step.
  • Stockists, traders, and suppliers who sell listed products fall under “supply”, “market” and “sell”.
  • Contractors, quantity surveyors, and project buyers who buy or use listed products on site fall under “buy” and “use”.

Source: sections 2 and 33D of Act 520.

A practical first step is to match a catalogue against the gazetted list in P.U. (A) 277/2026, rather than treating every line in the product index as a listed material.

PPS and the CCPM channel

PPS stands for Perakuan Pematuhan Standard (Certificate of Standard Compliance), the CIDB certificate for a listed material. Section 33D of Act 520 makes dealing in a listed material without CIDB certification an offence.

CIDB’s Certification of Construction Product and Material (CCPM) platform at ccpm.cidb.gov.my is the application channel.

Items industry players typically review after the amendment:

  1. The current Fourth Schedule in P.U. (A) 277/2026.
  2. Every SKU made, imported, or sold, marked against that list, with SKUs certified under the 2021 list re-checked against the standards now listed.
  3. For each listed SKU, the standard cited in the schedule. A certificate written against a standard the new list no longer names does not match it.
  4. PPS applications on CCPM where a listed SKU lacks a current certificate matching the amended standards.
  5. Mill certificates, test reports, and PPS copies held with the delivery file, which is how a contractor’s QS typically checks them at goods receipt.

A common procurement practice is to list PPS (number, standard, expiry) as a purchase-order condition on Fourth Schedule lines.

Penalties under Act 520

Under section 33D(2) of Act 520, a person who deals in Fourth Schedule materials without CIDB certification is liable on conviction to a fine of not less than RM10,000 and not more than RM500,000.

Checks contractors and QSes often run after the amendment

  1. Many teams circulate the Fourth Schedule amendment to procurement and to nominated suppliers for steel, concrete products, fibre or composite materials, and glass.
  2. A typical check is a written supplier confirmation of which SKUs are Fourth Schedule items, with current PPS copies.
  3. Many Bills of Quantities and material specifications cite PPS on delivery for listed products, in addition to an MS or BS number on the datasheet.
  4. For imported lines, PPS and Customs often run in parallel. The import duty and SST guide covers the tariff side.
  5. A typical register tracks PPS numbers against PO lines through the defects-liability period.

FAQ

When did the CIDB Fourth Schedule Act 520 amendment 2026 take effect in Malaysia?

On 1 August 2026, under paragraph 1(2) of P.U. (A) 277/2026.

What does the amended Fourth Schedule list?

Construction materials in 11 categories, from iron and steel to innovative products, each against its approved standards. The full schedule is in P.U. (A) 277/2026.

Who needs CIDB certification for a Fourth Schedule product?

Section 33D of Act 520 applies to anyone who deals in a listed material, and section 2 defines “deal” to include handling, using, manufacturing, supplying, marketing, transferring, selling, buying, importing and exporting. CIDB’s CCPM platform at ccpm.cidb.gov.my is the application channel for PPS.

What is the fine for dealing without CIDB certification?

Not less than RM10,000 and not more than RM500,000 on conviction, under section 33D(2) of Act 520.

Does PPS replace import duty or SST?

No. PPS is CIDB certification of a listed material, which section 33D of Act 520 requires before dealing in it. Import duty and SST are Customs charges under PDK 2025 and the Sales Tax Act. An imported Fourth Schedule product can need both. The import duty and SST 2025 guide covers the tariff side. CCPM is the PPS channel.

TAGS cidbact-520fourth-scheduleppsccpmregulatorymalaysia